Which statutory inspection do you need? LOLER, PUWER and PSSR compared

A typical workshop has a compressor, a forklift and a rack of slings. Each falls under a different set of regulations, with its own examination rules and its own timetable. This guide shows which rule covers which item, and when each one is due.

Last checked against the sources below on . General guidance, not legal advice.

The three regulations side by side

LOLER is the Lifting Operations and Lifting Equipment Regulations 1998. PUWER is the Provision and Use of Work Equipment Regulations 1998. PSSR is the Pressure Systems Safety Regulations 2000. The main difference between LOLER and PUWER is scope: LOLER covers equipment that lifts, and PUWER covers work equipment of every kind. PSSR covers equipment that holds pressure.

LOLER covers lifting equipment. PUWER covers work equipment of every kind. PSSR covers equipment that holds steam or pressurised gas. One machine can fall under two of them, which is why a forklift needs a lifting examination and also falls under the general work equipment rules.

What each regulation covers and asks for
LOLER 1998PUWER 1998PSSR 2000
CoversLifting equipment: work equipment for lifting or lowering loads, and accessories that attach loads to it, such as slings and chains (regulation 2)Any machinery, appliance, apparatus, tool or installation for use at workSystems holding a relevant fluid: steam, or gas above 0.5 bar over atmospheric pressure, and some high vapour pressure liquids (regulation 2)
Main dutyThorough examination by a competent person (regulation 9)Inspection where safety depends on installation or the equipment can deteriorate dangerously (regulation 6), alongside suitability, maintenance, training and guardingA written scheme of examination (regulation 8), then examination to that scheme by a competent person (regulation 9)
PaperworkWritten report with the particulars in Schedule 1. Dangerous defects are notified at once (regulation 10)A record of each inspection, kept until the next one (regulation 6(3))A signed, dated report sent to the user or owner within 28 days (regulation 9(3))

Which regulation covers your equipment

The table lists common workplace equipment. Intervals shown are the regulatory minimums. A competent person can set a different interval through an examination scheme, and some equipment needs examining sooner because of how it is used.

Common equipment and the regulation that covers its examination
EquipmentRegulationWhat the rules ask for
Forklift truck, or telehandler lifting loadsLOLER and PUWERThorough examination at least every 12 months, or every 6 months if it lifts people. PUWER covers maintenance, training and controls.
Cherry picker, scissor lift or other MEWPLOLER and PUWERIt lifts people, so thorough examination at least every 6 months.
Overhead crane or hoistLOLER and PUWERThorough examination at least every 12 months. Its slings and hooks fall under the accessories rule below.
Chain, wire or web sling, shackle, hook or eyeboltLOLERA lifting accessory, so thorough examination at least every 6 months.
Passenger or platform liftLOLERIt lifts people, so thorough examination at least every 6 months.
Goods liftLOLERThorough examination at least every 12 months.
Production machine with guards, interlocks and emergency stopsPUWERInspection at suitable intervals, set by risk assessment. Guarding and controls are checked against regulations 11 to 19.
Power pressPUWER, regulations 32 to 35Thorough examination at least every 12 months where it has fixed guards only, otherwise at least every 6 months (regulation 32(4)).
Ladder, working platform or fall-arrest systemWork at Height Regulations 2005, with PUWERPUWER regulation 6 does not apply to equipment covered by regulation 12 of the Work at Height Regulations, which asks for inspection at suitable intervals.
Air receiver or compressed air systemPSSR, with PUWER for the compressorA written scheme of examination, and examination to that scheme.
Steam boiler or steam steriliserPSSRSteam is a relevant fluid at any pressure, so a written scheme is needed.
Hydraulic systemPUWERHydraulic oils are not relevant fluids, so PSSR does not apply (HSE). Inspect to your risk assessment.
Roller shutter doorPUWERWork equipment, so inspected at suitable intervals set by risk assessment.

Equipment that is not on this list still falls into one of the three groups. Ask whether it lifts a load, whether it holds steam or gas under pressure, and then whether it is work equipment at all. In that order, the answers usually settle it.

Two rows have pages of their own. See Lifting Accessories Inspections for slings, chains and shackles, and pressure systems and the written scheme of examination for boilers and air receivers. For power presses and other machinery, the PUWER risk assessment and checklist is the place to start.

Examination, inspection, check: what each word means

The regulations use different words on purpose, and mixing them up is how a business ends up with the wrong paperwork.

The terms and who carries them out
TermWhat it isWho does it
Thorough examinationA systematic and detailed examination of the equipment and its safety-critical parts, ending in a written report. PSSR calls its version an examination.A competent person
InspectionA check that equipment can be operated, adjusted and maintained safely, and that deterioration is caught early. HSE says the need for it, and how often, comes from risk assessment.Someone suitably trained and competent, often the operator or maintenance staff
Pre-use checkA quick visual or functional check before the equipment is used, for example on a sling or a forklift's brakes and lights.The user
MaintenanceKeeping equipment in an efficient state, in efficient working order and in good repair (PUWER regulation 5).Maintenance staff or a contractor
TestingLoad or other tests, used only where the competent person judges them necessary. HSE notes that most lifting equipment needs no routine testing and some overload tests can damage it.A competent person

When each one is due

Routine examinations are only part of the picture. Each regulation also asks for an examination or inspection at certain moments in the life of the equipment.

What triggers an examination or inspection
TriggerLOLERPUWER (general)PSSR
Before first useThorough examination, unless the equipment is new and has a declaration of conformity under 12 months old (regulation 9(1))Inspection after installation, where safety depends on how it is installed (regulation 6(1))Where the scheme says so, before first use (regulation 8(3)(c))
After installation or assembly at a new siteThorough examination where safety depends on installation conditions (regulation 9(2))Inspection after assembly at a new site or location (regulation 6(1))Set by the written scheme
RoutineAt least every 6 months for lifting people and for accessories, every 12 months for other lifting equipment, or as an examination scheme sets (regulation 9(3))At suitable intervals, with no fixed period (regulation 6(2))Within the intervals in the written scheme (regulation 9(1))
After exceptional circumstancesEach time they occur, for example damage, a long period out of use or a major repair, as HSE explains (regulation 9(3)(a)(iv))Each time they occur, for example major modification or serious damage, as HSE explains (regulation 6(2)(b))Set by the written scheme
Between formal examinationsAn inspection by a competent person at suitable intervals, if appropriate (regulation 9(3)(b))Pre-use and routine checks as your risk assessment setsKeep the system maintained in good repair (regulation 12)
RecordsReports kept for set periods that depend on the type of examination and the equipment (regulation 11)Each inspection record kept until the next is made (regulation 6(3))The last report, and earlier ones if they help judge whether the system is safe (regulation 14)

When more than one applies

A forklift truck

The truck is lifting equipment, so LOLER requires a thorough examination and a report. The same truck is work equipment, so PUWER requires it to be suitable, maintained, fitted with working controls and driven by trained people. One examination covers the first duty. The other duties are yours to meet day to day.

A compressed air system

The air receiver, its pipework and the safety valve are a pressure system once the air is above 0.5 bar over atmospheric pressure, so they normally need a written scheme of examination. The compressor that feeds them is a machine, so its guards, controls and isolation fall under PUWER. Two sets of rules, two sets of records.

Who has to arrange it

LOLER and PUWER put the duty on the employer. Both also reach any person who has control of the equipment, to the extent of that control. A business that hires a machine in for months, and decides how and by whom it is used, picks up those duties for that period.

PSSR names the user of an installed system and the owner of a mobile system. HSE adds that a user of hired or leased pressure equipment should make sure a written scheme is in place and the examination certificate is current.

Compliance with all three means holding the paperwork each one asks for: the LOLER report of thorough examination, the PUWER inspection record and the PSSR examination report.

How Fox Engineering Safety can help

We carry out LOLER thorough examinations, PUWER inspections and PSSR examinations. We examine equipment and do not sell, hire or repair it, so the report reflects the condition of the equipment and nothing else. Reports are delivered digitally through our customer portal.

If you already know which regulation applies, go straight to the page for it: LOLER 1998 Thorough Examinations, PUWER Inspection & Risk Assessment or PSSR Inspection | Pressure Systems Safety Regulations 2000. For a checklist, use the LOLER compliance checklist for lifting equipment, or the PUWER checklist in the PUWER risk assessment and checklist guide for work equipment.

Sources

Duties, intervals and definitions on this page come from the legislation and HSE guidance listed here. Read the original when you need the exact wording.

Common questions

Questions people ask

Is a PUWER inspection the same as a LOLER thorough examination?

No. A LOLER thorough examination is a detailed examination by a competent person, with a written report that must contain the particulars in Schedule 1 of the regulations. A PUWER inspection under regulation 6 is a check that the equipment can still be operated, adjusted and maintained safely, and its frequency comes from your risk assessment. PUWER itself asks for a thorough examination in one place only: power presses.

Does lifting equipment need a PUWER inspection as well?

Not under regulation 6, which excludes work equipment for lifting loads. Lifting equipment is examined under LOLER instead. PUWER still applies to it for other duties: HSE says maintaining lifting equipment in a safe condition is a PUWER requirement.

Who has to arrange the examination, the owner or the hirer?

LOLER and PUWER duties fall on the employer and on anyone who has control of the equipment, to the extent of that control, so for long-term hire it is usually the user. Under PSSR the duty falls on the user of an installed system and the owner of a mobile system. HSE says the user of hired or leased pressure equipment should check that a written scheme is in place and the examination certificate is current.

Can the person who maintains the equipment also examine it?

HSE says the competent person for a LOLER thorough examination should not be the person who carries out routine maintenance of the same equipment, because they would then be assessing their own work. They also need to be independent and impartial enough to examine without fear or favour.

What happens if the examiner finds a defect?

Under LOLER the examiner must tell you straight away about any defect that is or could become a danger to people, and you must not use the equipment until it is put right. If there is an existing or imminent risk of serious personal injury, a copy of the report goes to the enforcing authority. Under PSSR the report names any repairs needed and the date by which they must be done, and the system must not run past that date unless they are complete.

Where does the risk assessment come in?

Every employer must make a suitable and sufficient assessment of workplace risks under regulation 3 of the Management of Health and Safety at Work Regulations 1999. For PUWER inspections it is the starting point: HSE says the need for inspection, and how often, should be set through risk assessment.